50 Free PMP Practice Questions — Project Management Professional
Preparing for the PMP certification? These 50 free practice questions cover the three PMP domains.
Domain 1: People (Questions 1–21)
Question 1
A project team is experiencing conflict between two senior developers over technical approach. What is the best conflict resolution approach?
a) Force a decision quickly
b) Collaborate to find a win-win solution
c) Avoid the conflict
d) Escalate to management
Show Answer
Answer: b) Collaborate to find a win-win solution
Explanation: The collaborating/problem-solving approach seeks a win-win solution. It's the preferred approach for important issues where both parties' concerns need to be addressed.
Question 2
Which leadership style is most appropriate for a mature, experienced team?
a) Autocratic
b) Delegating (laissez-faire)
c) Transactional
d) Coaching
Show Answer
Answer: b) Delegating (laissez-faire)
Explanation: Situational leadership theory suggests delegating is best for mature teams with high competence. The leader provides minimal supervision and trusts the team to self-organize.
Question 3
A stakeholder with high power and low interest should be managed with what strategy?
a) Manage closely
b) Keep satisfied
c) Keep informed
d) Monitor
Show Answer
Answer: b) Keep satisfied
Explanation: Power/Interest Grid: High Power + Low Interest = Keep Satisfied. High Power + High Interest = Manage Closely. Low Power + High Interest = Keep Informed.
Question 4
How many communication channels exist in a team of 8 people?
a) 28
b) 56
c) 16
d) 64
Show Answer
Answer: a) 28
Explanation: Communication channels = n(n-1)/2 = 8(7)/2 = 28. Each additional team member significantly increases communication complexity.
Question 5
What is the primary responsibility of a servant leader?
a) Making all project decisions
b) Removing impediments and empowering the team
c) Assigning tasks to team members
d) Reporting to stakeholders
Show Answer
Answer: b) Removing impediments and empowering the team
Explanation: Servant leadership focuses on the team's growth, removing obstacles, and creating an environment where the team can perform at its best.
Question 6
A team member is consistently missing deadlines. What should the project manager do first?
a) Escalate to HR
b) Remove them from the team
c) Have a private conversation to understand the root cause
d) Assign the work to someone else
Show Answer
Answer: c) Have a private conversation to understand the root cause
Explanation: The first step is a private, respectful conversation to understand the reason for poor performance. Performance issues may stem from skill gaps, personal issues, or unclear expectations.
Question 7
Which Tuckman stage follows the "Storming" phase?
a) Forming
b) Norming
c) Performing
d) Adjourning
Show Answer
Answer: b) Norming
Explanation: The five stages: Forming → Storming (conflict) → Norming (cohesion) → Performing (high productivity) → Adjourning (closure).
Question 8
What is the best way to reward a project team?
a) Individual bonuses for top performers
b) Team-based recognition aligned with what motivates them
c) Public recognition only for the project manager
d) No rewards — it's their job
Show Answer
Answer: b) Team-based recognition aligned with what motivates them
Explanation: Team-based rewards promote collaboration. Effective rewards align with what the team values (recognition, time off, training, bonuses) and celebrate collective achievements.
Question 9
A project manager needs to influence a stakeholder who opposes the project. What is the best approach?
a) Ignore the stakeholder
b) Escalate to executive sponsor immediately
c) Build trust through active listening, understand their concerns, and find alignment
d) Proceed without their support
Show Answer
Answer: c) Build trust through active listening, understand their concerns, and find alignment
Explanation: Influence begins with understanding the stakeholder's perspective. Active listening, empathy, and finding common ground are more effective than confrontation or escalation.
Question 10
Which emotional intelligence component involves understanding others' emotions?
a) Self-awareness
b) Self-regulation
c) Empathy
d) Social skills
Show Answer
Answer: c) Empathy
Explanation: Empathy is the ability to understand and share the feelings of others. It's a key component of emotional intelligence, enabling better stakeholder management and team leadership.
Questions 11–20
[Reduced for length — full 50-question set available in the full practice exam]
Domain 2: Process (Questions 22–40)
Question 22
What is the critical path?
a) The shortest path through the schedule
b) The longest path through the schedule, determining minimum project duration
c) A path with the most expensive activities
d) A path with the most float
Show Answer
Answer: b) The longest path through the schedule, determining minimum project duration
Explanation: The critical path is the sequence of activities that represents the longest path through the project. It determines the earliest possible completion date. Any delay on the critical path delays the project.
Question 23
If EV = $50,000, PV = $60,000, and AC = $55,000, what is the schedule variance (SV)?
a) $5,000
b) -$5,000
c) -$10,000
d) $10,000
Show Answer
Answer: c) -$10,000
Explanation: SV = EV - PV = $50,000 - $60,000 = -$10,000. Negative SV means the project is behind schedule. CPI = EV/AC = 50,000/55,000 = 0.91 (over budget).
Question 24
Which risk response strategy is being used when a team buys insurance?
a) Avoid
b) Mitigate
c) Transfer
d) Accept
Show Answer
Answer: c) Transfer
Explanation: Risk transfer shifts the financial impact of a risk to a third party (insurance, fixed-price contracts, warranties). The risk still exists but someone else bears the financial consequences.
Question 25
What is a work breakdown structure (WBS)?
a) A list of activities
b) A hierarchical decomposition of the total scope of work
c) A schedule diagram
d) A cost estimate
Show Answer
Answer: b) A hierarchical decomposition of the total scope of work
Explanation: The WBS breaks the project scope into progressively smaller, manageable deliverables and work packages, forming the foundation for schedule, cost, and resource planning.
Question 26
What is the difference between quality control and quality assurance?
a) QC is process-focused; QA is product-focused
b) QA is process-focused; QC is product-focused
c) They are the same
d) QA is done by the team; QC by management
Show Answer
Answer: b) QA is process-focused; QC is product-focused
Explanation: Quality Assurance (QA) focuses on the processes used to build the product (prevention). Quality Control (QC) focuses on inspecting the product to verify quality (inspection).
Question 27
What is the purpose of a change request?
a) Documenting team meetings
b) Formal proposal to modify a project baseline
c) Reporting project status
d) Assigning resources
Show Answer
Answer: b) Formal proposal to modify a project baseline
Explanation: A change request is a formal proposal to modify any document, deliverable, or baseline. It's processed through integrated change control.
Question 28
Which procurement contract places the most risk on the seller?
a) Cost-Plus-Fixed-Fee (CPFF)
b) Time and Materials (T&M)
c) Firm Fixed Price (FFP)
d) Cost-Plus-Incentive-Fee (CPIF)
Show Answer
Answer: c) Firm Fixed Price (FFP)
Explanation: FFP contracts place cost risk on the seller (they must deliver at a fixed price regardless of actual costs). Cost-reimbursable contracts place risk on the buyer.
Question 29
What is the purpose of a project charter?
a) Detailed project schedule
b) Authorizes the project, assigns the PM, and provides high-level requirements
c) Team assignments
d) Risk register
Show Answer
Answer: b) Authorizes the project, assigns the PM, and provides high-level requirements
Explanation: The charter provides formal authorization, assigns the project manager, defines high-level scope/objectives, and links the project to business strategy.
Question 30
What is float (slack) in project scheduling?
a) The amount of time an activity can be delayed without affecting the project end date
b) The cost buffer for an activity
c) The resource buffer
d) The difference between planned and actual cost
Show Answer
Answer: a) The amount of time an activity can be delayed without affecting the project end date
Explanation: Total float is the time a task can be delayed without delaying the project. Critical path tasks have zero float. Free float is delay without affecting the next task.
Questions 31–40
[Full 50-question set with EVM calculations, risk management, procurement, and stakeholder analysis available in complete practice exam]
Domain 3: Business Environment (Questions 41–50)
Question 41
What is the primary purpose of a business case?
a) Tracking project progress
b) Justifying the project investment through cost-benefit analysis
c) Assigning the project manager
d) Creating the project schedule
Show Answer
Answer: b) Justifying the project investment through cost-benefit analysis
Explanation: The business case provides financial justification for the project, including cost-benefit analysis, ROI, NPV, IRR, and alignment with organizational strategy.
Question 42
Which compliance regulation affects projects handling credit card information?
a) GDPR
b) HIPAA
c) PCI DSS
d) SOX
Show Answer
Answer: c) PCI DSS
Explanation: PCI DSS (Payment Card Industry Data Security Standard) applies to projects handling credit card data. HIPAA is for healthcare, GDPR for European personal data, SOX for financial reporting.
Question 43
What is the difference between a project and a program?
a) A project is temporary; a program is a group of related projects
b) A program is temporary; a project is ongoing
c) They are the same
d) Programs are smaller than projects
Show Answer
Answer: a) A project is temporary; a program is a group of related projects
Explanation: A project is a temporary endeavor with a unique deliverable. A program is a group of related projects managed together to achieve benefits not possible individually.
Question 44
What is the purpose of a benefits realization plan?
a) Defining how and when project benefits will be measured and achieved
b) Creating the project budget
c) Assigning team members
d) Defining project constraints
Show Answer
Answer: a) Defining how and when project benefits will be measured and achieved
Explanation: The benefits realization plan defines target benefits, measurement metrics, timing of benefit delivery, and who is responsible for measuring them.
Question 45
Which organizational structure gives the project manager the most authority?
a) Functional
b) Weak matrix
c) Balanced matrix
d) Projectized
Show Answer
Answer: d) Projectized
Explanation: In a projectized organization, the PM has full authority over the project budget and team. Functional gives least authority, matrix is in between.
Questions 46–50
[Full set covering compliance, organizational change (Kotter's 8 steps), portfolio management, and benefits realization available in complete practice exam]
How Did You Score?
- 0–25 correct: Review the PMP Exam Guide.
- 26–40 correct: On track. Focus on weak domains.
- 41–50 correct: Ready for the exam!
Access all PMP practice questions →
Related Articles
Bereit, dein Wissen zu testen?
Probiere unsere Übungsprüfungen mit Hunderten von realistischen Fragen aus.
Üben starten →